Cochlear Head Office NSW

2008 - 2009
Macquarie Park NSW 2113
Completed
project image

Scope Delivered

Seven-Storey Cochlear Head Office
Project Overview

Painting Cochlear’s seven-storey head office in Macquarie Park

Our team delivered painting works for the seven-storey Cochlear head office in Macquarie Park, NSW. The project was completed between 2008 and 2009, with Watpac Constructions NSW as the head contractor. Our scope covered the building’s internal offices, corridors and lobbies, as well as external façades, balconies, slab edges and stairs.

The works included painting to walls, ceilings, soffits, bulkheads, doors, frames, skirtings and window reveals, along with line marking and signage, timber fencing and specialist epoxy coating applications.

Our team won the painting tender package based on price and reputation.

Scope of Works

Internal and external painting across the building

  • Painting to internal walls throughout offices, corridors and lobby areas
  • Painting to ceilings, soffits and bulkheads
  • Painting to doors, frames and skirtings
  • Painting to internal window reveals
  • Painting to the external façade
  • Painting to balconies, slab edges and stairs
  • Line marking and signage
  • Painting to timber fencing
  • Application of specialist coatings
  • Epoxy applications
The Challenges

Maintaining sufficient manpower

Maintaining sufficient manpower was a key requirement of the project. Painting progressed from the initial coats through to the final coats, moving sequentially from Level 1 to Level 7. External façade works then progressed from the roof to ground level.

  
Our Approach

How the painting works were sequenced

  1. 1

    Internal painting from Level 1 to Level 7

    Initial painting works through to final coats were carried out progressively from Level 1 through to Level 7

  2. 2

    Detailed internal finishes

    The team completed painting to internal walls, ceilings, soffits, bulkheads, doors, frames, skirtings and window reveals across the building.

  3. 3

    External façade works

    External painting works were carried out progressively from the roof towards ground level, including the external façade, balconies, slab edges and stairs.

  4. 4

    Specialist works and line marking

    The scope also included epoxy applications, line marking and signage.

  5. 5

    Timber fencing

    Painting to timber fencing was included as part of the overall project scope.